Phase 2 of ER Expansion Underway Soon

Starting April 2, Phase 2 of the ER Expansion will kick into high gear. Site clean up and demo will begin and carry throughout the first weeks of April, followed by electrical, HVAC duct work, drywall and more.

If the state comes on Monday, March 26th and passes Phase 1 of the new ER, work could begin sooner. However, the hospital still needs 48 hours to move into the completed Phase 1 facility before demo and work on Phase 2 can begin. So, the earliest that Phase 2 can begin is Thursday, March 29.